TransStroy's multi-disciplinary specialisation enables it to implement complex projects that include several types of infrastructure construction, fundamentally different in terms of technology and specialists, work organisation and techniques used.


LONG-TERM AND CURRENT PROJECTS
Rocky soil transportation and crushing works to the required fraction
Rocky soil transportation and crushing works to the required fraction
Oil loading terminal of the Severn Bay seaport, Taimyrsky Dolgana-Nenets Municipal District, Krasnoyarsk Krai
23.12.2023 - present

Crushing and sorting works of rocky soil in the amount of 700 thousand cubic metres to fill the object Oil loading terminal of the seaport "Severn Bay".
2022
Preparation of the construction site of the ethane gas complex in Ust-Luga
Preparation of the construction site of the ethane gas complex in Ust-Luga
Site: Gas processing complex as part of the ethane gas processing complex at Ust-Luga 

Site preparation works for the construction of the ethane gas complex in Ust-Luga settlement

At the present moment the unfit soil is being excavated and removed, grubbing is in progress, the base for the embankment is being prepared and the embankment is being filled with sand with layer-by-layer compaction.

The work on the site involves 25 units of machinery; the company has built its own dormitory for the workers.

The planned scope of soil development at the site is more than 900,000 cubic meters.

The work is due to be completed by the 4th quarter of 2023.
Rubble crushing works and rehabilitation of cargo areas at the Solombala Terminal TLC
Rubble crushing works and rehabilitation of cargo areas at the Solombala Terminal TLC
Customer: Arctic-Consulting-Service company

Crushed stone production and cargo storage area redevelopment for general cargo

Transport and logistics complex "Solombala Terminal", Arkhangelsk

June-August 2021
Facilities construction at Salmanovskoye oil and gas condensate deposit, October 2019 - present
Facilities construction at Salmanovskoye oil and gas condensate deposit, October 2019 - present
Project customer: Nova

In October 2019 TransStroy LLC started construction of facilities as part of the Salmanovskoye field development.

Soil excavated in the quarry and transported to the backfill site - over 750,000 m3
Site backfill with layer-by-layer compaction - more than 750,000 m3
Thermal insulation layer installed - more than 200,000 m2

In the planning period 2019-2023, 14 sites are to be built, with a total volume of 1,300,000 m3 of different soil categories.

The engineering of construction projects in this field is a promising area for the company.

The climate of the construction area is severely continental with harsh and prolonged winters.Nevertheless, all conditions have been created for employees to live and work comfortably in the Far North conditions.

The company is using state-of-the-art equipment and machinery on the site. The number of staff involved in construction and assembly work and living in an autonomous wagon camp exceeds 100 people. More than 50 units of equipment are involved in backfilling of sites, well pads, wells and access roads.

Work is carried out in a two-shift mode.
Basalt stone crushing and grading, Franz Josef Land
Basalt stone crushing and grading, Franz Josef Land
The work has been carried out since 2014 to the present.

Crushed stone production up to 8000 m<sup>3</sup> per day.
2020 - 2021
Compensatory reforestation, June-August 2021
Compensatory reforestation, June-August 2021
Compensatory reforestation works, June-July 2021

Customer: Severalmaz

Plesetsk district, Arkhangelsk region
Total area - 68 hectares
147 000 closed-root pine seedlings
Cargo storage area redevelopment at TLC Solombala Terminal, June-August 2021
Cargo storage area redevelopment at TLC Solombala Terminal, June-August 2021
Customer: Arctic-Consulting-Service company

Cargo storage area redevelopment for general cargo and pipes of large diameter
Transport and logistics complex "Solombala Terminal", Arkhangelsk

Total area of works - 23 000 m2
June-August 2021
Rocky soil transportation and crushing works to the required fraction
Rocky soil transportation and crushing works to the required fraction
Offshore Superfacility Construction Yard
Belokamenka, Murmansk region
Customer: Nova
2019 - May, 2020

Total volume of processed soil - more than 180 000 m3.

Machines and equipment involved:

Volvo articulated haulers;
Volvo excavators with rock buckets;
Volvo front loader;
Sandvik crusher plant;
Metso Lokotrack screen.

The climate conditions of the OSCY operation area are in the sub-arctic zone of the European part of the Russian Federation.
2018 - 2019
OFFSHORE SUPERFACILITY CONSTRUCTION YARD. COASTAL AREA VERTICAL PLANNING, SLOPE RESHAPING, ROCK EXCAVATION
OFFSHORE SUPERFACILITY CONSTRUCTION YARD. COASTAL AREA VERTICAL PLANNING, SLOPE RESHAPING, ROCK EXCAVATION

Belokamenka, Murmansk region

Customer: Novatek-Murmansk

2017-2019 гг.

 

Vertical levelling of the coastal area with slope reshaping to increase stability and rock excavation in layers of up to 15 m.

The total excavation volume is more than 12,000,000 m3.

Digging and hauling up to 8,000,000 m3 of rock a day.

 

The machines and equipment involved:

Volvo and Terex articulated dump trucks;

Scania and Tatra carrier dump trucks;

Volvo and Cat excavators with rock buckets;

CAT bulldozers;

Sandvik crusher plant.


Height difference during excavation - up to 60 metres.


The coastal areas have a complex rocky surface with a sharply rugged profile.


The climatic conditions of the OSCY construction area are a sub-arctic zone of the European part of the Russian Federation.

Mechanised excavation for the construction of an apartment building and an educational facility
Mechanised excavation for the construction of an apartment building and an educational facility
Work performed:
Mechanised excavation with dewatering, loading onto dump trucks and hauling to a landfill - 95,000 m3.
Dismantling of underground structures of technogenic nature. Manual reclamation of soil between piles.

Objects: Multi-apartment building with built-in premises and built-in and attached car park. Preschool Educational Institution.

Customer: Technadzor SPB (St. Petersburg)
2011 - 2017
Loading area construction
Loading area construction
Customer: MRTS-Stroymontazh

Volume of crushed rock backfill – 67855 m2

Geotextile base course – 67855 m2
Machinery transport services
Machinery transport services

Our company provides services for the transport of machinery by sea, road and rail.

MINING, CRUSHING, SORTING, RECLAMATION AT THE DEPOSIT
MINING, CRUSHING, SORTING, RECLAMATION AT THE DEPOSIT
2014-2015:
  • Stump removal on an area of 31.5581 ha with subsequent burning outside the fire-hazardous period
  • Overburden removal over an area of 31.5581 ha
  • Crushing and screening of sand-gravel material to a size of 40-70 mm and 20-40 mm

The volumes of the extracted granular sand material:

2014: 450,000m3

2015: 193,022 m3


Pit excavation works
Pit excavation works
CUSTOMER: Titan-Development
2012
Digging with further transportation and disposal: 75 000 m3

Sand backfill with compaction to a compaction factor: 0.95 - 30000 m3

Drainage: 400 m
Duration of works: 3 months
Haul road construction
Haul road construction

CUSTOMER: Solombala Pulp and Paper Mill

2011

 

Total area: 60 000 m2

Backfill volume: 48 000 m3

Duration of work: 2 months